[Op1st-dc-alerts] [mghpcc-alerts] X-Ray inspection testing at the MGHPCC – limited facility access after 5PM Wed 3/20/24

mghpcc-alerts mghpcc-alerts at mghpcc.org
Thu Mar 14 16:59:38 EDT 2024


Notice of planned X-Ray inspection of new chilled water pipes for the MHGPCC computer room.
No one other than the inspection contractors will be allowed beyond the lobby and office spaces during testing.

Estimated Start: 5:00PM  Wednesday March 20,2024 
Estimated End:  Midnight Wednesday March 20,2024

Tenant Impact
--------------------
No service impact is expected

Description
—————
A contractor will be performing X Ray inspection to verify the quality of the welds on chilled water pipes that are ready for installation in the MGHPCC Computer Room.  

To ensure safe and efficient completion of this operation, no one other than the inspection contractors will be allowed beyond the lobby and office spaces during testing.

The work will take place in the area of the data center where construction is currently under way.