[Op1st-dc-alerts] [mghpcc-alerts] Completed: **Potentially Service-Affecting** Electrical Work Monday 3/18/24 – Thursday 3/21/24
mghpcc-alerts
mghpcc-alerts at mghpcc.org
Thu Mar 21 18:25:31 EDT 2024
The Electrical work in the MGHPCC Computer room that was scheduled for this week is now complete.
Thanks for your patience over the past few days..
======March 14 Alert=======
Reminder, with some revisions.
The MGHPCC plans to to power down the switchboards that feed power to the following areas of the MGHPCC data center to allow electrical work in the computer room.
Pod R1-PA (odd side only)
Pod R2-PA
Pod R3-PB (odd side only)
Pod R6-PA
Pod R8-PA (tape library)
Pod R6-PB
Pod R6-PC
Pod R9-PA
Entrance Room 1
Entrance Room 2
Estimated Start: 7:00 AM Monday March 18, 2024
Estimated End: 5:00 PM Thursday March 21, 2024
Tenant Impact
--------------------
There may be brief periods of time when we will ask everyone to leave the Computer Room for safety (e.g. when a switchboard is being powered up).
Computing, Storage, and Networking equipment in the areas named above should not be affected if it has been properly configured for operation with power cords attached to both the “A” and “B” PDUs in its rack.
Equipment outside the areas named above should not be affected, independent of configuration.
There is elevated risk for the entire Computer Room while the work is being done.
Description
—————
Schedule is expected to be:
* Mon 3/18, after 7AM: Disable power to the B side bus bars in the areas named above
* Tue 3/19, after the electrical work is done: Restore B side power.
* Wed 3/ 20, after 7AM: Disable power to the A side bus bars in the areas named above.
* Thu 3/21, after the electrical work is done: Restore A side power.
More information about the op1st-dc-alerts
mailing list